School Operations

Last changed on Wed, 12/31/1969 - 18:00
gdp-dc0017-0035-001
Topic
School Operations
Summary
Regarding the arrangement and condition of the dormitories, the hospital, employee's building power plant, and boiler house.
gdp-dc0017-0047-001
Topic
School Operations
Summary
Regarding employees of the large boys' building, three of whom are under inspection due to unharmonious work and reports of mistreatment.
gdp-dc0017-0002-001.png
Topic
School Operations
Summary
Regarding the report of the capacity of the dormitories, classrooms, and dining hall of the school plant; addition to the girls' quarters.
gdp-dc0017-0033-001
Topic
School Operations
Summary
Regarding the description of the condition of the boys' dormitory, the girls' dormitory, hospital, the employees' building, heating and power plant, and the arrangement of the school campus.
gdp-dc0017-0007-001.png
Topic
School Operations
Summary
Regarding drawings that cannot be sent due to carpenter's absence.
gdp-dc0017-0049-001
Topic
School Operations
Summary
Regarding cleaning the building thoroughly.
gdp-dc0017-0039-001
Topic
School Operations
Summary
Regarding the permit for an additional expenditure of $1,996 for miscellaneous expenses.
gdp-dc0017-0008-001.png
Topic
School Operations
Summary
Regarding unapproved changes in the gymnasium.
gdp-dc0017-0025-001
Topic
School Operations
Summary
Regarding the return of blueprints of the boys' dormitory, attic floor plan, and response to ventilation criticisms.
gdp-dc0017-0023-001
Topic
School Operations
Summary
Regarding the forwarding of blueprints showing the school campus.